CISDI’s latest success at Rizhao
Date:2019/6/18 Source: CISDI
CISDI’s latest success at Rizhao
Shandong Steel’s
Rizhao steelmaking plant has announced the successful hot commissioning of its
hot metal KR-process desulphurisation system 4.
All major
production facilities at the plant are now operational.
CISDI is the
plant’s main contractor. Its unique purging de-slagging development has been
applied to the four KR de-S systems. Key features are a very simple structure,
easy maintenance, facilitated slag skimming, more efficient desulphurising and
a shorter treatment cycle.
The last two de-S
systems were constructed while four BOF were in operation.
CISDI faced
numerous difficulties. The project team had to work to a challenging time schedule
to avoid any interference with production at the plant, and assembly of
reusable devices had to be done in situ.
But thanks to the
team’s well-organised management and experiences learned during construction of
the first two KR de-S systems, difficulties were overcome and project targets
were achieved.
KR de-S system 4 in
action at Shandong Steel’s Rizhao steelmaking plant